CEDAR POINT WIND

Operating

Wind power plant

Capacity
252 MW
Primary fuel
Wind
County
Lincoln County
Operator
CEDAR POINT LLC
Status
Operating
Commissioned
2011
EIA plant ID
57315
Generators
1
Technology
Onshore Wind Turbine
Net generation (2024)
671 GWh
Capacity factor (2024, EIA nameplate)
30%
Data vintage
EIA-860 2024 final; EIA-923 2022-2024 final
Coordinates
39.4109, -103.6949

See it on the map

CEDAR POINT WIND, a 252 MW Wind power plant in Lincoln County, Colorado. Operated by CEDAR POINT LLC, commissioned 2011.

How CEDAR POINT WIND compares

With 252 MW of capacity, CEDAR POINT WIND ranks 20th among the 114 operating power plants Bywatts maps in Colorado and 2nd of the 17 operating Wind plants in the state. It accounts for about 11% of Colorado's operating Wind capacity and 1.6% of all operating capacity in the state. Nationally it is the 25th-largest of the 708 operating Wind plants in the database. Commissioned in 2011, it is newer than 88% of the 111 operating Colorado plants with a recorded commissioning year. It shares Lincoln County with 3 other operating plants, including LIMON WIND I and LIMON WIND II.

EIA-860 lists 1 generator at the site with 252 MW of nameplate capacity, all onshore wind turbine technology. Net generation was 671 GWh in 2024 (a 30% capacity factor), up 36% from 2022.

Grid neighborhood

The nearest named substation is CEDAR POINT (230 kV), about 2.2 miles away; the closest transmission line found within 10 miles is a 230 kV line owned by PUBLIC SERVICE CO OF COLORADO, under 0.1 miles away. Another 3 operating power plants totaling 554 MW sit within 25 miles; the largest is LIMON WIND I (200 MW, Wind).

Computed by Bywatts from HIFLD power plant, substation and transmission line records and EIA-860/923 survey data; distances are straight-line. Sources and methodology

Weather peril exposure

CEDAR POINT WIND is a 252 MW wind power plant in Lincoln County, CO, operated by CEDAR POINT LLC, commissioned in 2011. Lincoln County carries critical modeled catastrophe exposure in the FEMA National Risk Index, scoring 4.6 of 5 at the 91st national percentile. Hail is the leading peril, rated Relatively Low by FEMA at the 92nd percentile.

The Bywatts loss layer is calibrated to solar PV hardware, so it is not applied to a wind plant. The ratings below are the FEMA National Risk Index county hazard ratings for this location.

4.6 of 5Modeled catastrophe exposure
CriticalExposure band
HailLeading peril
Very LowFEMA county risk rating

Lincoln County hazard ratings

PerilFEMA ratingNational percentilePeril scoreEvents per year
HailRelatively Low92nd4.7 of 56.3
TornadoVery Low87th4.5 of 52.6
Riverine floodingVery Low86th4.4 of 50.61
WildfireVery Low74th4.0 of 5<0.01
Strong windRelatively Low71st3.8 of 51.4
Winter weatherRelatively Low71st3.8 of 59.5
EarthquakeVery Low37th2.5 of 5<0.01
Ice stormVery Low30th2.2 of 50.03
LightningVery Low20th1.8 of 550.1
Heat waveVery Low16th1.6 of 50.34

Perils not assessed in Lincoln County

These perils carry no usable National Risk Index figure for this county, so they are excluded from the scoring rather than scored zero. A zero would claim the peril was assessed and found benign.

PerilWhy it is not scored
HurricaneFEMA rating is "Not Applicable" for this county
Coastal floodingFEMA rating is "Not Applicable" for this county

Model hail, wind and flood exposure for Lincoln County in the weather risk calculator

Ratings are the FEMA National Risk Index county hazard ratings; the peril score is a Bywatts transform of the FEMA national percentile. Full data sources and the solar vulnerability methodology are in the weather risk calculator.

Modeled estimate for screening and negotiation. Built from FEMA National Risk Index county hazard data and a solar vulnerability layer documented above. Not a quote, a binder, or actuarial advice, and not a substitute for a carrier's own model. Hazard data: FEMA National Risk Index December 2025, synced 2026-07-24. Resolution is county level, not site level.