CEREDO GENERATING STATION

Operating

Natural Gas power plant

Capacity
519 MW
Primary fuel
Natural Gas
County
Wayne County
Operator
APPALACHIAN POWER CO
Status
Operating
Commissioned
2001
EIA plant ID
55276
Generators
6
Technology
Natural Gas Fired Combustion Turbine
Net generation (2024)
492 GWh
Capacity factor (2024, EIA nameplate)
11%
Data vintage
EIA-860 2024 final; EIA-923 2022-2024 final
Coordinates
38.3677, -82.5341

See it on the map

CEREDO GENERATING STATION, a 519 MW Natural Gas power plant in Wayne County, West Virginia. Operated by APPALACHIAN POWER CO, commissioned 2001.

How CEREDO GENERATING STATION compares

With 519 MW of capacity, CEREDO GENERATING STATION ranks 9th among the 31 operating power plants Bywatts maps in West Virginia and is the largest of the 2 operating Natural Gas plants in the state. It accounts for about 60% of West Virginia's operating Natural Gas capacity and 3.4% of all operating capacity in the state. Nationally it is the 322nd-largest of the 1,185 operating Natural Gas plants in the database. Commissioned in 2001, it is newer than 64% of the 31 operating West Virginia plants with a recorded commissioning year. Its operator, APPALACHIAN POWER CO, runs 6 operating plants in West Virginia totaling 4,805 MW. It shares Wayne County with one other operating plant, BIG SANDY PEAKER PLANT.

EIA-860 lists 6 generators at the site with 519 MW of nameplate capacity, all natural gas fired combustion turbine technology. Net generation was 492 GWh in 2024 (an 11% capacity factor), up 24% from 2022.

Grid neighborhood

The nearest named substation is BAKER (765 kV), about 13.4 miles away; the closest transmission line found within 10 miles is a 138 kV line owned by APPALACHIAN POWER CO, under 0.1 miles away. Another 4 operating power plants totaling 2,847 MW sit within 25 miles; the largest is HANGING ROCK ENERGY FACILITY (1,288 MW, Natural Gas).

Computed by Bywatts from HIFLD power plant, substation and transmission line records and EIA-860/923 survey data; distances are straight-line. Sources and methodology

Weather peril exposure

CEREDO GENERATING STATION is a 519 MW natural gas power plant in Wayne County, WV, operated by APPALACHIAN POWER CO, commissioned in 2001. Wayne County carries moderate modeled catastrophe exposure in the FEMA National Risk Index, scoring 2.4 of 5 at the 34th national percentile. Riverine flooding is the leading peril, rated Relatively Moderate by FEMA at the 99th percentile.

The Bywatts loss layer is calibrated to solar PV hardware, so it is not applied to a natural gas plant. The ratings below are the FEMA National Risk Index county hazard ratings for this location.

2.4 of 5Modeled catastrophe exposure
ModerateExposure band
Riverine floodingLeading peril
Relatively LowFEMA county risk rating

Wayne County hazard ratings

PerilFEMA ratingNational percentilePeril scoreEvents per year
Riverine floodingRelatively Moderate99th5.0 of 52.3
WildfireRelatively Low68th3.7 of 5<0.01
Ice stormRelatively Moderate57th3.3 of 50.38
LightningRelatively Low52nd3.1 of 548.4
Winter weatherRelatively Low46th2.8 of 58.5
Heat waveRelatively Moderate45th2.8 of 54.5
HurricaneVery Low44th2.8 of 50.02
EarthquakeVery Low44th2.8 of 5<0.01
HailRelatively Low41st2.7 of 53.2
Strong windRelatively Low39th2.6 of 52.1
TornadoRelatively Low18th1.7 of 50.08

Perils not assessed in Wayne County

These perils carry no usable National Risk Index figure for this county, so they are excluded from the scoring rather than scored zero. A zero would claim the peril was assessed and found benign.

PerilWhy it is not scored
Coastal floodingFEMA rating is "Not Applicable" for this county

Model hail, wind and flood exposure for Wayne County in the weather risk calculator

Ratings are the FEMA National Risk Index county hazard ratings; the peril score is a Bywatts transform of the FEMA national percentile. Full data sources and the solar vulnerability methodology are in the weather risk calculator.

Modeled estimate for screening and negotiation. Built from FEMA National Risk Index county hazard data and a solar vulnerability layer documented above. Not a quote, a binder, or actuarial advice, and not a substitute for a carrier's own model. Hazard data: FEMA National Risk Index December 2025, synced 2026-07-24. Resolution is county level, not site level.