JONES BLUFF

Operating

Hydro power plant

Capacity
82 MW
Primary fuel
Hydro
County
Autauga County
Operator
USCE-MOBILE DISTRICT
Status
Operating
Commissioned
1975
EIA plant ID
6131
Generators
4
Technology
Conventional Hydroelectric
Net generation (2024)
244 GWh
Capacity factor (2024, EIA nameplate)
34%
Data vintage
EIA-860 2024 final; EIA-923 2022-2024 final
Coordinates
32.3249, -86.7854

See it on the map

JONES BLUFF, an 82 MW Hydro power plant in Autauga County, Alabama. Operated by USCE-MOBILE DISTRICT, commissioned 1975.

How JONES BLUFF compares

With 82 MW of capacity, JONES BLUFF ranks 43rd among the 64 operating power plants Bywatts maps in Alabama and 16th of the 23 operating Hydro plants in the state. It accounts for about 2.5% of Alabama's operating Hydro capacity and 0.3% of all operating capacity in the state. Nationally it is the 207th-largest of the 1,243 operating Hydro plants in the database. Commissioned in 1975, it is newer than 50% of the 64 operating Alabama plants with a recorded commissioning year. Its operator, USCE-MOBILE DISTRICT, runs 2 operating plants in Alabama totaling 183 MW. It shares Autauga County with 4 other operating plants, including E B HARRIS ELECTRIC GENERATING PLANT and TENASKA LINDSAY HILL GENERATING STATION.

EIA-860 lists 4 generators at the site with 82 MW of nameplate capacity, all conventional hydroelectric technology. Net generation was 244 GWh in 2024 (a 34% capacity factor), down 12% from 2022.

Grid neighborhood

The closest transmission line found within 10 miles is a 115 kV line owned by ALABAMA POWER CO, under 0.1 miles away. Another 6 operating power plants totaling 3,462 MW sit within 25 miles; the largest is E B HARRIS ELECTRIC GENERATING PLANT (1,304 MW, Natural Gas).

Computed by Bywatts from HIFLD power plant and transmission line records and EIA-860/923 survey data; distances are straight-line. Sources and methodology

Weather peril exposure

JONES BLUFF is an 82 MW hydro power plant in Autauga County, AL, operated by USCE-MOBILE DISTRICT, commissioned in 1975. Autauga County carries moderate modeled catastrophe exposure in the FEMA National Risk Index, scoring 2.2 of 5 at the 31st national percentile. Riverine flooding is the leading peril, rated Relatively Low by FEMA at the 73rd percentile.

The Bywatts loss layer is calibrated to solar PV hardware, so it is not applied to a hydro plant. The ratings below are the FEMA National Risk Index county hazard ratings for this location.

2.2 of 5Modeled catastrophe exposure
ModerateExposure band
Riverine floodingLeading peril
Relatively LowFEMA county risk rating

Autauga County hazard ratings

PerilFEMA ratingNational percentilePeril scoreEvents per year
Riverine floodingRelatively Low73rd3.9 of 50.93
HurricaneRelatively Low71st3.9 of 50.08
TornadoRelatively Moderate71st3.8 of 50.51
EarthquakeRelatively Low66th3.6 of 5<0.01
LightningRelatively Moderate53rd3.1 of 568.5
Strong windRelatively Low48th2.9 of 51.3
Heat waveRelatively Moderate43rd2.7 of 59.5
Ice stormRelatively Low42nd2.7 of 50.40
WildfireVery Low39th2.6 of 5<0.01
HailRelatively Low38th2.5 of 52.6
Winter weatherVery Low9th1.4 of 51.4

Perils not assessed in Autauga County

These perils carry no usable National Risk Index figure for this county, so they are excluded from the scoring rather than scored zero. A zero would claim the peril was assessed and found benign.

PerilWhy it is not scored
Coastal floodingFEMA rating is "Not Applicable" for this county

Model hail, wind and flood exposure for Autauga County in the weather risk calculator

Ratings are the FEMA National Risk Index county hazard ratings; the peril score is a Bywatts transform of the FEMA national percentile. Full data sources and the solar vulnerability methodology are in the weather risk calculator.

Modeled estimate for screening and negotiation. Built from FEMA National Risk Index county hazard data and a solar vulnerability layer documented above. Not a quote, a binder, or actuarial advice, and not a substitute for a carrier's own model. Hazard data: FEMA National Risk Index December 2025, synced 2026-07-24. Resolution is county level, not site level.