LINDEN COGEN PLANT

Operating

Natural Gas power plant

Capacity
974 MW
Primary fuel
Natural Gas
County
Union County
Operator
COGEN TECHNOLOGIES LINDEN VENT
Status
Operating
Commissioned
1992
EIA plant ID
50006
Generators
9
Technology
Natural Gas Fired Combined Cycle
Net generation (2024)
5,625 GWh
Capacity factor (2024, EIA nameplate)
66%
Data vintage
EIA-860 2024 final; EIA-923 2022-2024 final
Coordinates
40.6325, -74.2154

See it on the map

LINDEN COGEN PLANT, a 974 MW Natural Gas power plant in Union County, New Jersey. Operated by COGEN TECHNOLOGIES LINDEN VENT, commissioned 1992.

How LINDEN COGEN PLANT compares

With 974 MW of capacity, LINDEN COGEN PLANT ranks 5th among the 130 operating power plants Bywatts maps in New Jersey and 3rd of the 25 operating Natural Gas plants in the state. It accounts for about 11% of New Jersey's operating Natural Gas capacity and 6.7% of all operating capacity in the state. Nationally it is the 99th-largest of the 1,185 operating Natural Gas plants in the database. Commissioned in 1992, it is older than 78% of the 128 operating New Jersey plants with a recorded commissioning year. It shares Union County with 9 other operating plants, including PSEG LINDEN GENERATING STATION and UNION COUNTY RESOURCE RECOVERY.

EIA-860 lists 9 generators at the site with 974 MW of nameplate capacity, all natural gas fired combined cycle technology. Net generation was 5,625 GWh in 2024 (a 66% capacity factor), up 7% from 2022. Its generators came online between 1992 and 2002.

Grid neighborhood

The nearest named substation is WAVERLY, about 4.1 miles away; the closest transmission line found within 10 miles is a 230 kV line owned by PUBLIC SERVICE ELEC & GAS CO, about 0.1 miles away. Another 76 operating power plants totaling 16,225 MW sit within 25 miles; the largest is RAVENSWOOD (2,625 MW, Natural Gas). Within 50 miles are 29 mapped data centers; the nearest is Telehouse - Teleport Center (New York) in Staten Island, about 2.8 miles away.

Computed by Bywatts from HIFLD power plant, substation and transmission line records, EIA-860/923 survey data and PeeringDB data center locations; distances are straight-line. Sources and methodology

Weather peril exposure

LINDEN COGEN PLANT is a 974 MW natural gas power plant in Union County, NJ, operated by COGEN TECHNOLOGIES LINDEN VENT, commissioned in 1992. Union County carries low modeled catastrophe exposure in the FEMA National Risk Index, scoring 1.3 of 5 at the 6th national percentile. Earthquake is the leading peril, rated Relatively Moderate by FEMA at the 79th percentile.

The Bywatts loss layer is calibrated to solar PV hardware, so it is not applied to a natural gas plant. The ratings below are the FEMA National Risk Index county hazard ratings for this location.

1.3 of 5Modeled catastrophe exposure
LowExposure band
EarthquakeLeading peril
Relatively HighFEMA county risk rating

Union County hazard ratings

PerilFEMA ratingNational percentilePeril scoreEvents per year
EarthquakeRelatively Moderate79th4.2 of 5<0.01
HurricaneRelatively Moderate69th3.7 of 50.11
Riverine floodingRelatively High69th3.7 of 53.4
Ice stormVery High64th3.6 of 50.74
Coastal floodingRelatively Moderate49th3.0 of 53.8
Winter weatherVery High43rd2.7 of 511.0
Strong windVery High30th2.2 of 56.4
WildfireVery Low23rd1.9 of 5<0.01
LightningVery High21st1.9 of 533.7
TornadoRelatively Moderate19th1.8 of 50.04
HailVery Low8th1.3 of 52.4
Heat waveRelatively Moderate8th1.3 of 59.4

Model hail, wind and flood exposure for Union County in the weather risk calculator

Ratings are the FEMA National Risk Index county hazard ratings; the peril score is a Bywatts transform of the FEMA national percentile. Full data sources and the solar vulnerability methodology are in the weather risk calculator.

Modeled estimate for screening and negotiation. Built from FEMA National Risk Index county hazard data and a solar vulnerability layer documented above. Not a quote, a binder, or actuarial advice, and not a substitute for a carrier's own model. Hazard data: FEMA National Risk Index December 2025, synced 2026-07-24. Resolution is county level, not site level.